Tomorrow will be an estimate. What should I consider? I know that the estimates should be as detailed as possible. And there shall be shown a list of works and bill of materials. How to avoid mistakes?
The estimate must necessarily take into account the amendment of the payment amount.
That is, for example laid down in the estimate of $ 100. This cost should be no more, for example 10%. If this figure repair team "pereplyunet" - this is not your concern. This should be clearly specified in the contract that there was no ambiguity.
Next: Be sure to divide the work into stages. At the end of each stage must be checked against the estimates and the resulting mortgaged.
Do not settle, if you will be offered inflate the cost estimates that motivate this by the fact that m building materials are rising.
In any case, all construction materials will be purchased by the other team costs than provided in the estimates. Do not pay any attention to it, so, unfortunately, "accepted."
Tip: Check the number of used building material that you deliver. Sometimes what you pay for building materials for another apartment.
See not only checks but also on real materials.
Ideally, you want an independent brigade, who would control the procurement and use of building materials. Payment of his work will cost you less
-
Of course, it is best to find an experienced quantity surveyor, who wisely make an estimate taking into account the technology of construction and repair processes, and agree it with the construction team.
But since you decided to do everything ourselves, advice - buy yourself though, would guide a civil engineer (flow of materials on general construction and finishing work). It reflects the composition of the work and the required amount of material (including the correction k). Also on each package of materials given its cost, you can find more information on the Internet.
If builders will argue that consumption of material they have to get above, you can safely rely on low qualifications of such specialist and ask to replace it with another. After this question is usually removed.
Contract with a construction team to enter required. Denial of drawing up the contract should cause concern. The contract specifies the total cost, deadlines, penalties. Desirable to specify more that work is performed by appropriately qualified professionals and in accordance with SNIP.
-
Generally, as practice shows, is not never been so estimates sootvetsvovala reality, and it's not that the working poor or can not be considered - although Russia is full of such! Just over each project, which will be done, often otkazyvayutsya customers to think for themselves or another variant of estimates, as the document oficial worth the money, not small (this is, roughly speaking, it is necessary to draft in square meters, to take into account all the wiring all the nuances, which each version is complete) and a lot of customers who otkazyvaetsya pay for the estimate, saying it is not needed and everything is clear, count on a sheet and let us rather quickly repair ...
Here is the simplest example - has been tasked to put tile in the hallway and bathroom, a hallway tile, bathroom - the other ... under the door leading from the hallway to the bathroom butt of different tiles. Everything seems easy. Was covered buckle under the tile on the beacons virtually zero + - 2 mm and dried up until the screed (three weeks) ordered it, got the idea that she wants to e-mail. floor heating in bathrooms, what it does? She calls the company's handler, he puts a warm floor and that we have in the end? Tile is no longer placed under the comb and the fiber (or warm floor had to fill leveling) and this is extra. work and add. materials, and estimates that no, she explained it, but in response said that the leveling is not necessary, put on a layer - but even in this case, adhesive consumption uvelichivaetsya and the cost of work too, but try to explain that the styling has become more expensive ...
So it is not always blame the workers that the estimates are not met, this I mean that if you started a renovation or construction, it is better to think ahead. It's not as difficult as it seems in fact. Spend a few days to clarify all the details of your repair and you may find it easier and working!
And in most estimates and matters relating to her, um ... honestly say it depends on with what you have contacted the firm for the superintendent do not have any difficulty to enter in the estimate of what will be actually done or what quantity of material that actually be used and then he will take for another repair ... the Council here, only one - the consultant from the outside, independent and professional in their field!