Continuation of the series "House with his own hands," the story of the construction of the attic floor, and ceilings between the floors. Construction began with the installation armopoyasa greater than its part designed to support the wooden floor beams.
Built formwork, lined hydraulics in a circle, put a grid of 3 mm, with a cell 50 mm poured concrete, the thickness is about 5-8 cm
installation of formwork
For assembling and filling zones used here are Climbing, fast to install, fast to make out offensively that had not previously seen such a lot of problems would dare to them.
Forest
This time was smarter, quickly hit the road and paid the money in advance, bought peenoblok good, strong, smooth and on time this morning to pay - in the evening he went up by 20%, saved some money
has delivered foam block
In armopoyase, the project must be walled anchor for fixing consoles such special stops (decorative and load-bearing element), which retained stem the roof (1.5 meters), this propylene grinder with a diamond wheel to deepen and put the anchor of the 14 mm rod made notches on the wall in the end.
gash mounting anchors
Location and pitch anchors - the project
here so they stick
Started putting the series on 5 rows of masonry had been hired three Dzhamshut (most are no longer under power), under close my control, the ranks are growing. In some lower-left opening for mounting rails, each 45 cm
assembly series
Cook floor beams, the board bought 50 * 200, Senezh ognebio (green) is situated on the ground and began training ends - Senezh smear, smear bitumen primer (butt not smear like the impossible)
cook overlap
These are the beams, cook and put them in a pile.
ends of the beams
Beams napilil in size 6 and 3.3 meters (half of 6 meters at 45 grams), pick up, 6-meter overlap span of 5 meters and 3.3 meter span of 3 meters (15 cm inside the wall) to fasten galvanized bolts, immediately smear Senezh. End wrap roofing material, minted mortar in the wall.
laying the first beams
Stitching boards on the bolts on the middle wall, in what this part of the (not very reliable) if the enhanced
reliance is not so hot but what's better than nothing
Beam mount further in the future, in the span of 5 meters will be mounted booster board, as this section of beams and the step is too small for the load of living rooms.
increasing overlap
On the middle wall laying on the roofing material, processing until only nodes dalshe entire board will be processed.
Here they are, beams
Mount all the beams start manufacturing seysmopoyasa under the hanging rafters attic floor
ready overlapping
Began to work on carving grinder with diamond wheel groove around the attic wall to a depth of 4 cm
carve a groove grinder
Then, the usual old ax (immediately evident is in the photo) wall riding clobber on the block, choosing the slot on the depth of 5-7 cm, it was funny from the
pulled out of the groove penobeton
From the rafters bearing the future roof armopoyas will be more powerful, with the confrontation of both vertical and Straining efforts (in part) for this napilil pieces of foam block and put a groove height of 15 cm
laying out a piece of foam blocks
In the groove put rebar AIII 10 mm, 3 rod (1 and 2 below the top) and anchors for consoles (the top of the console)
reinforcement in the zone
In the zone of the pediment two packed rod, he will have a tensile force from the lateral part of the belt
Seen from the side gables
Additionally, the project in the zone put the anchor leg on each rafter bars 10 mm threaded the letter G.
anchor for rafters
Armopoyas completely flooded, + anchor immediately inserted for fastening mauerlata
filled armopoyas
For the installation of the gable hired three Dzhamshut previously put the label of the pediment in the space of tow, the angle and height determined according to the project, mark the box.
top of the gable
That front is growing, manufactured formwork for casting bridges, along the lines of the lower - on 1 floor, fittings AIII 10 mm 3 pieces, as seen in the picture window will be from the bevel side
windows
After pouring the jumper with my constant control and participation (after all, the cycle .... With his hands ... .. ") goes back to Day 1, on arrival found that's the horror if I had a weapon, then the story would not have had years 15, for killing 3 people in a state of temporary insanity. Chinese Pagoda - it is! Naplyunuv on this matter further, dismissed Dzhamshut, started making the porch (pictured top)
Chinese Pagoda
The time has come, and thought how to fix it, for it knocked down the grinder all the excess and lined by a thread! SAM - SAM IS!
front after the alteration
To return to normal height and the strengthening of the additional grid overlaid on the front and top pieces napilennyh blocks, turned and higher and stronger and safer
further strengthened the front
That was such a smooth and beautiful pediment gable has been reviewed on the ridge reinforced bed for the skating bar on the roof of the future
here already Lucci!
Meanwhile, finished porch.
done!
In this story is finished, the next story will be the story of a house roof.
No comments:
Post a Comment