So. Waiting for a stable spring heat, I proceeded to the construction of the first in his life foundations. Then just a photo with a description of each stage:
1. Removed the upper layer of vegetation, the depth of a bayonet.
2. Filled sand. Shed. Stamped.
3. Knocked up and set out the formwork dyuymovki. Height of 20 cm from the main reception bar 50x50, strengthened scraps valves.
4. Poured a second layer of sand. Aligned irregularities shed. Stamped.
5. Laid waterproofing. 2 are mutually perpendicular to the layer with overlap ruberoyda 30-40 cm
6. Insulation. 3 cm foam. In fact, not so much for warmth as for ease of ordering concrete (without the volume of 3.2 cube with him - exactly 3 cube). The top is covered with one layer ruberoyda with overlap of 50 cm
7. Reinforcement. Armature d12 and d16 through one, a cell of 20 cm can be used only d12, just bought the first 16, then buy more for 12. Frequently asked questions, whether it is possible to knit reinforcement plastic cable ties. Possible, most importantly not greedy and buy a long tie, they are wider and thicker, stronger, respectively. The entire frame is linked 2,5 hours for four hands. Distansery between the upper and lower grille - a chimney brick. Between bottom bars and the base - split by quarters 5cm Pavement. The lower and upper grid connected to each other wire in the 15 sites for the greater rigidity of the framework.
8. Came to the mixer. 10 minutes carefully poured concrete cube 3 M-300 on the crushed granite. Until recently there was the fear that the shuttering would not stand. Needlessly worried, everything went with a bang. The driver slowly distilling machine and tray from corner to corner, concrete practically oozed himself, take away almost did not have to. After proshtykovali scraps valves, lined the edge of the casing and covered film.
9. A week later.
10. Plate treated with bituminous paint. The foundation is ready.
UPD: What would I have now done differently.
Firstly, after the full fall-winter-spring understood that overdone with descent. Very low buried plate, almost level with the ground, will now have to bear additional expenditure for waterproofing the joint plate-wall to protect themselves against the penetration of meltwater in the spring of drainage around the perimeter. IMHO, a plate - it is a superficial foundation, rather than shallow-buried (if there is no cellar or basement, of course).
Secondly, the next time I will make a footing. It is easier to lay waterproofing, including surfaced, in addition, it is somewhat evens basis.
Thirdly, special spacers for stacking fixture. Brick, of course, also does not hurt, but with them as something beautiful and correct. =)
No comments:
Post a Comment