I came up with the idea to attach a canopy to the house to the terrace, rain did not fall. And grapes, planted on the southern facade of the house, in need of support, for which we should serve as a trellis, which is located between the uprights canopy. In the end, should get some sort green arbor near the house, which protects not only from the rain, but the heat on hot summer days.
So, it should be easy construction of the entire length of the facade of the house, ie, 6m, the width determines the length of the roofing material, it leaves Ondury 2 m in length, taking into account the slope of the roof is 1.8m, height is determined so that the roofing sheets are firmly under the dashboard, between the first and second floor.
For the manufacture of such a canopy need 4 steel pipes 60h60h3 4 m long, 2 boards 50h150h6000, 7 boards 50h150h2000, 7 25h100h6000 boards, threaded rod M8 and M8 nuts, screws, hex head, so-called wood grouse, 8h140.
With the onset of warm weather, I took up implementation of this project. Were initially marked places for the installation of poles, posts and drilled with a diameter of 150 mm and a depth of 1.5m. In the wells are inserted into sleeves of tar paper, set racks of steel pipe and poured concrete. Racks are aligned vertically in two planes using level or plumb. Everything seems to be simple, but as in any business there are some nuances of which I tell you, because usually it is omitted in the description of various designs. So, about the nuances of technology. Before installing the pillars of their upper edges welded lid size 60x60. After that, in each column are drilled on three cross-hole 8 mm in diameter, at 50, 1000, 1950 mm from the top. Set in a hole two extreme column.
Take the two boards 25h100h6000, departing from their ends to 150 mm, 8 mm drill holes. Inserting the upper and lower holes in the pillars trim pins, these pins are strung on prepared board, and tightens the nut. All of this construction are putting vertically, and using gidrouroven set top posts on the same horizontal, driving one of the pillars in the ground a little. Pour the concrete pillars, controlling their vertical in both planes. Day you can relax or do other things while the concrete is slightly grow up.